How to Install a Metal Roof: Step-by-Step Panels, Trim & Timing

Knowing how to install a metal roof comes down to sequence: deck, underlayment, eave and rake trim, panels, closures, ridge cap. We estimate metal roofing for general contractors, roofing subcontractors and owners, and deliver an Excel workbook, a PDF summary and marked-up drawing pages so every panel count and fastener line traces back to a measurement rule.

  • Panel counts traced to measured roof squares
  • Underlayment, fastener and trim quantities itemized
  • Waste and overlap rules stated on the sheet
  • Marked-up drawings show where each quantity came from

Upload your plans

Send drawings and a short scope. You get a fixed price before any work starts.

Framer in a hard hat working on top of a wood stud wall

What are the main steps to install a metal roof?

To install a metal roof, you install eave and rake trim, roll out underlayment, set the first panel square to the eave, fasten at the specified spacing, overlap each panel, then fit closures, ridge cap and flashing. Panel type, pitch and substrate set the fastening pattern.

How to Install a Metal Roof: The Sequence That Keeps Water Out

A metal roof is built as a water-shedding stack, not a single product. Each layer depends on the one below it: the roof deck carries the load, underlayment handles what drives past the panels, panels move water to the eave, and trim closes every edge and penetration. Reverse that order and you get callbacks — usually at the valley or the pipe boot, rarely in the field of the panel.

Scope the metal roof installation steps before anyone orders material. On a re-roof, decide whether the existing shingle course stays (a tear-off is cleaner and lets you inspect decking) or the new panels go over a prepared substrate. Panel profile sets the fastening path: exposed fastener panels screw through the face, standing seam panels use concealed clips. Lead times on cut-to-length panels and color-matched trim often drive the schedule more than the crew does.

Knowing how to install a metal roof in the right order matters more than speed: strip or prepare the deck, inspect and repair sheathing, install underlayment and ice/water shield, set eave and rake trim, lay panels, close the ridge with a ridge cap, then flash valleys, walls, and penetrations. Trim goes on in the order water would reach it, so lower components lap under the ones above.

For costing, the metal roof installation cost per square varies with profile, panel gauge, trim count, and roof complexity. Our roofing estimates break the job into line items — panels, clips, closure strip, underlayment, flashing, labor hours — so you can see where the money sits. The calculator below converts a base wage, burden, overtime share, and crew hours into a loaded labor rate, which is the number most bids get wrong.

Install sequence and what each stage depends on
StageComponentDepends onCommon failure if skipped
1Tear-off or substrate prepDeck inspectionRot hidden under new panels
2Deck repair and purlinsPanel span tableOil canning, loose fasteners
3Underlayment and ice/water shieldDry weather windowLeaks at penetrations
4Eave and rake trimPanel layoutWater tracking behind fascia
5Panels and clipsTrim setMisaligned seams, short panels
6Ridge cap and closuresPanel run completeBlow-off at the ridge
7Valley, wall, and pipe flashingPanels fastenedLeaks at transitions

Loaded labor rate calculator

Loaded rate
$31/hr
Blended with overtime
$32/hr
Labor hours
320
Crew labor cost
$10,279

Burden covers payroll taxes, workers’ compensation, insurance and benefits; it varies by state, trade and company. Overtime is priced at time and a half.

Exposed fastener vs standing seam: two different install paths

An exposed fastener panel is screwed through the face at every purlin or deck line, with a gasketed washer under each head. The screws sit in the flat of the panel, and the next panel overlaps that edge, so the fastener spacing and the panel overlap are set by the manufacturer's span table. It is faster and cheaper per square, and the trade-off is that the washers are the wear point.

Standing seam is a concealed fastener system: clips hold the panel to the deck and the seams are folded or crimped shut, so no fastener penetrates the weather surface. Panels run long, often eave to ridge, which means thermal movement is real and the clips must allow it. Seam crimping and hemming at the eave and ridge are separate line items in labor. Both profiles go over the same deck and underlayment; the difference is in clips, trim, and the tools on the truck.

What you need before day one: permits, panel order, crew size

Confirm the permit and the local code edition with the building department before you strip anything; the inspector will want to see deck attachment and underlayment before the panels cover them. Order panels from field measurements, not plan dimensions, and add trim to the same order — eave trim, rake trim, ridge cap, valley flashing, closure strip. Panels cut short cannot be stretched.

Crew size follows panel length and roof pitch. Long panels on a steep slope need more hands on the lift and at the eave, and the calculator below lets you test crew size against hours. Plan a dry window for the underlayment stage; an open deck overnight is a risk you are accepting, not a step to skip. If you would rather hand the sequence to an estimator, that is where how to install a metal roof turns into a priced scope.

Measure and Order: Takeoff Numbers You Can Trace

Every order starts with roof area in squares, where one square equals 100 sq ft of roof surface, not floor area. Measure the footprint from the plan, then divide by the cosine of the roof pitch to get the sloped area. A 40 ft by 30 ft footprint is 1,200 sq ft of plan area; at a 6:12 pitch the slope factor is about 1.118, so the roof area is 1,200 × 1.118 = 1,342 sq ft, or 13.42 squares. Field measure the same way with the actual overhang included.

Panel length math follows the slope: measure from the eave line to the ridge along the roof surface, add the eave overhang and any ridge allowance the profile needs, and round to the manufacturer's increment. Keep each panel run on one line of the takeoff so a reader can re-check length, count, and total linear feet.

Waste is a judgment call, not a fixed rule. Typical waste on a simple gable runs low single digits; hips, valleys, and dormers push it higher. Add trim as linear feet, not squares: eave trim equals eave length, rake trim equals rake length, ridge cap equals ridge length, and closure strip follows the same runs. Count fasteners from the manufacturer's pattern — screws per square foot of panel times panel area, plus clips at the clip spacing.

This is where metal roofing panel installation and the diy metal roof vs contractor decision separate. A DIY crew saves labor but owns the takeoff errors, and a short panel order is a second delivery. An exposed fastener panel with a simple gable is the friendliest first job; standing seam with valleys is not. The same discipline carries into larger assemblies, which is why metal building and pemb estimating treats purlin runs and panel counts as separate lines. For a structured walk-through of the measuring method, see how to estimate roofing. The square-foot budget calculator below takes your own base hard cost per sq ft and applies soft-cost, contingency, and escalation percentages — it holds no prices of its own, so the numbers come from your takeoff.

Illustrative takeoff for a 1,200 sq ft footprint at 6:12 pitch
ItemUnitQuantityArithmetic
Plan areasq ft1,20040 ft × 30 ft
Slope factor—1.1186:12 pitch
Roof areasq ft1,3421,200 × 1.118
Roof areasquares13.421,342 ÷ 100
Waste at 8%squares1.0713.42 × 0.08
Order quantitysquares14.4913.42 + 1.07
Ridge caplinear ft40ridge length
Eave trimlinear ft80two 40 ft eaves

Square-foot budget calculator

Hard cost
$444,000
Soft costs
$53,280
Contingency
$49,728
Escalation
$21,880
Budget total
$568,888
All-in per sq ft
$237

Enter your own base rate from a recent bid, cost book or estimator. The default values are placeholders for the math, not market prices.

Roof area, slope, and panel length math

Write the arithmetic on the takeoff sheet so the number is traceable: footprint length × width, then × slope factor, then ÷ 100 for squares. For panel length, use the raked distance from drip edge to ridge plus overhang, and note the pitch and the measurement date. If you are working from a plan, cross-check the roof deck dimensions against the wall dimensions before you trust either. Knowing how to install a metal roof starts with knowing exactly how many squares and linear feet of trim the roof holds, because the panel order is cut once.

Waste, trim, and fastener quantities

List waste as a separate line with its percentage and the reason, so a reviewer can challenge it. Trim quantities come from measured runs: eave, rake, ridge, hip, valley, and wall transitions each get a length and a piece count. Fasteners get a count per square from the panel manufacturer's pattern, then multiplied by squares and rounded up to the box. A quantity takeoff built this way survives a change order because every line shows its unit and source, and it gives a general contractor a defensible basis for how to estimate construction projects as a general contractor.

Prep the Deck, Underlayment, and Flashing

Deck preparation is the cheapest insurance on the job. Renail or re-screw loose sheathing, replace delaminated panels, and check that the roof deck is flat enough for the panel profile — standing seam metal roof installation shows every dip as oil canning. Where the panel spans purlins instead of solid deck, set purlin spacing from the manufacturer's span table for the panel gauge and design load, and keep the purlins straight and in plane.

Ventilation belongs in this stage. Confirm intake at the eave and exhaust at the ridge before the ridge cap closes the roof, because retrofitting vent after the panels are on is a demolition task. On a re-roof over shingles, the substrate has to be built up so the new panel plane is true; the old shingle course is not a flat surface.

Underlayment laps follow the slope: higher laps over lower, with the lap width from the manufacturer's instructions. Synthetic underlayment is the common choice over a full deck; ice and water shield goes at the eaves, in valleys, and around penetrations where the code edition requires it. Fasten through the underlayment into the deck, not into the previous layer.

Flashing order follows water: valley flashing first, then eave and drip edge, then wall and step flashing woven with the panels, then pipe boots and other penetrations. Each panel overlap at a transition should shed onto the piece below it. Any guide on how to install a metal roof spends most of its length here, because on a cut-up roof the field goes fast and the transitions do not. Our professional trade estimating services price these stages as separate line items so the labor is visible.

Flashing and underlayment order, bottom of the roof up
StepComponentUnitRule of thumb
1Valley flashinglinear ftSet before panels, full length
2Ice/water shield at eavelinear ftSelf-adhered, confirm extent with code
3Synthetic underlaymentsquaresLaps shed downhill
4Drip edge and eave trimlinear ftStraight line for panel start
5Panels and panel clipssquaresClip spacing per span table
6Step and wall flashinglinear ftWoven with each panel course
7Pipe boots and penetrationseachCollar seated on profile
8Ridge cap and closure striplinear ftVent path left open

Decking, purlins, and ventilation

On solid deck, the sheathing carries the clips and the underlayment; on purlins, the panel spans between supports and the spacing is a structural number, not a preference. Check fastener embedment into the deck and the purlin gauge against the panel manufacturer's table. Ridge vent and eave intake are set before the ridge cap goes on, and the closure strip at the ridge must not block the vent path.

Synthetic underlayment and ice/water shield

Roll synthetic underlayment horizontally with laps facing downhill and stagger the end laps. Ice and water shield is a self-adhering membrane at the eave, in valleys, and around penetrations; confirm the required extent with the local building department, since code editions differ. Walk the membrane down by hand or roller so it bonds — a loose lap is a future leak path.

Valley, eave, and wall flashing

Valley flashing goes in before any panel and must be wide enough to take the panel edge plus the lap. Eave trim and drip edge set the panel start line, so check them for straight before the first panel goes down. Wall and step flashing are woven as each panel course is set, and pipe boots go on after the panel is fastened, with the boot collar seated on the profile. This is the stage where how to install a metal roof is decided in practice: the flashing sequence, not the panel count, sets the pace.

Install the Panels, Fasteners, and Trim

Before the first panel goes up, snap a chalk line at the eave parallel to the ridge and check it against the rake on both ends. A panel that starts out of square compounds across the whole run, and it shows up later as a widening gap at the rake trim. Set the first panel, check the eave overhang and the line, then fasten it and use it as the reference for every panel after it.

Work from the manufacturer's published installation manual, not from memory or a supplier's verbal advice. The manual states panel gauge, clip or screw spacing, fastener type, and the maximum span over purlins for your wind zone. Those figures are what an inspector and a warranty administrator will check, so keep the manual on site and note the revision date on your daily log.

A concealed fastener system hides the clips under the seam, while an exposed fastener panel drives screws through the face. Both depend on the same discipline: correct fastener spacing, correct torque, and a straight run. If you are weighing a panel upgrade mid-project, the point to decide is before the deck is covered, which ties into the replacement triggers covered below.

Panel alignment, overlap, and clip spacing

For standing seam, place a panel clip at every purlin or as the manual directs, typically no more than 24 inches on center along the seam, and set each panel fully engaged before moving on. The metal roof panel overlap and fastening pattern for exposed fastener panels usually runs one major rib plus one minor rib, with screws on the flat between ribs. Fasten from the eave toward the ridge so panels can move outward at the eave under thermal movement. Never stretch a panel to close a gap; lift it and re-set the line.

Fastener placement and torque

Drive self-drilling screws with a gasketed washer straight and perpendicular, so the washer compresses evenly without cupping or splitting. Over-torque crushes the washer and leaves a path for water; under-torque leaves the washer loose. On exposed fastener panels, screws go in the flat of the panel, not in the rib, unless the manual says otherwise. Set a clutch on the driver and test the first few screws on scrap panel before you commit to a full run.

Ridge, hip, rake, and penetration details

Ridge cap, rake trim, and eave trim each need a closure strip or profile filler matched to the panel so wind-driven rain cannot enter under the trim. Seal pipe boots and other penetrations with the boot's own flashing and a bead of sealant under the flange, then fasten the flange with pancake screws into the deck. Leave the lower edge of each trim piece open where the manual calls for drainage, and check every lap so water runs over the lower piece, never behind it.

Is It the Right Time to Replace Your Metal Roof?

A metal roof rarely fails all at once. It shows a pattern: rust at the cut edges and fastener holes, fasteners backing out of the purlin or deck, chalky or flaking coatings, and interior staining that appears after wind-driven rain rather than every storm. Age alone is a weak signal, because a well-detailed 40-year panel can outlast a poorly installed 50-year panel.

Walk the roof and mark each defect on a plan view. Count fasteners that spin or sit proud, measure the length of rusted seams, and photograph the underside at the leak. That record is what turns a vague worry into a repair-or-replace decision, and it is the same record an estimator needs to price the work. It also feeds directly into a house construction estimate when the roof is part of a larger scope, and into the cost to replace a roof on a 1200 sq ft house when the roof is the whole job.

Signs a metal roof is failing

Backed-out or spinning self-drilling screws mean the fastener lost its bite, often from a washer that failed or a deck that swelled. Rust that has perforated the panel is a replacement signal; surface rust at a scratch is not. Coated panels can lose their finish and chalk, which is cosmetic until the base metal starts to corrode. Interior leaks concentrated at valleys, penetrations, and the eave trim usually point to flashing rather than the panel field. If the roof was installed over shingles, check whether corrugated metal roof installation over shingles left the old layer trapping moisture against the new panel.

Repair vs full replacement

Price a spot repair first: replace the failed fasteners with larger-diameter screws and new gasketed washers, re-seal the flashing, and add ice and water shield at the repair zone if the underlayment is compromised. Compare that number against a full tear-off and re-roof, and weigh the remaining service life of the panel field. If more than a small share of the panels show perforation or the fasteners are failing across the whole plane, repair becomes a recurring cost and replacement wins. If the defects sit in one valley or one penetration, repair is usually the better call.

Cost, Inspection, and What to Verify Before You Pay

A metal roof estimate should read like a bill of materials, not a single lump sum. Ask for the panel type and gauge, the trim schedule, the underlayment product, the fastener type and count, labor hours, equipment, and disposal. When an item is missing, the contractor either forgot it or plans to add it later as a change order. A traceable takeoff through a quantity takeoff keeps each of those lines tied to a measured area and a stated rule.

Material prices move. Steel mill products rose sharply in the twelve months to the latest Producer Price Index reading, and plastic construction products and lumber also moved, which is why a panel quote from last quarter may not hold. Labor rates for roofers and sheet metal workers come from published wage data. That is why we price from national average unit costs adjusted with those published series and reviewed by an estimator.

To start, request a free quote and attach your drawings.

Line items that belong in a metal roof estimate

Panels are priced per square of covered roof, with waste added for hips, valleys, and short runs. Trim and flashing are priced by the linear foot: rake trim, eave trim, ridge cap, valley flashing, and each pipe boot. Underlayment is priced by the square, with ice and water shield at the eaves and valleys. Fasteners are counted by type, including the gasketed washer screws and the pancake screws for trim. Labor, equipment, and tear-off disposal are separate lines. Commonly omitted items include closure strips, touch-up paint, and the purlin or furring needed to correct an uneven substrate.

Final inspection and warranty paperwork

Walk the finished roof with the contractor and check fastener lines for straightness, trim laps for direction, and every penetration for a sealed flange. Look for oil canning across the panel field, which is a flatness issue rather than a leak, and confirm the contractor documented it before installation. Confirm the metal roof underlayment and fasteners match the spec sheet, and that the metal roof trim and flashing installation was done to the manual. Register the manufacturer's warranty in your name, keep the panel and fastener invoices, and hold final payment until the punch list is closed and the warranty certificate is in hand.

Frequently Asked Questions

How much does it cost to install a metal roof per square foot?

There is no single national rate, because the number per square is built from the panel type, gauge, seam spacing, trim count, deck condition and tear-off scope. Standing seam with concealed clips and a full underlayment system prices differently from an exposed fastener panel screwed through the ribs. We quote the fee per project after reviewing the plans, and the estimate shows each line with its unit and source.

Can you install metal roofing over existing shingles?

Sometimes, but the decision is made on the deck, not on the shingles. A common approach is to strip the old covering, inspect and repair the roof deck, then lay synthetic underlayment or ice and water shield before the panels. Building over an existing layer adds weight and hides rot, so confirm what your local code and the panel manufacturer allow before you order material.

How long does a metal roof last compared to asphalt shingles?

Service life depends on panel gauge, coating, fastener type and climate, so treat any single number with caution. Asphalt shingles are commonly replaced far sooner than a properly detailed metal roof, and exposed fastener panels need washer and screw checks that standing seam does not. Salt air, hail and roof pitch all move the answer, so ask the manufacturer for the warranty terms on the specific panel.

What is the difference between exposed fastener and standing seam metal roofing?

Exposed fastener panels are screwed through the face of the sheet with gasketed washers, so the fastener is visible and the panel is cheaper to install. Standing seam panels use concealed clips and raised seams crimped together, which lets the metal move with thermal expansion and leaves no fastener through the weather surface. Standing seam costs more per square but carries fewer penetration points to maintain.

How do you know when it's time to replace a metal roof instead of repairing it?

Replace when the failure is systemic: widespread fastener back-out, rust through the panel, failed washers across whole runs, or seams that no longer close. A single lifted panel, a torn pipe boot or a local flashing leak is a repair. Check the underside for water staining and the fasteners for loose or missing screws before you decide, and price the repair against a full replacement.

What fasteners and underlayment are required for a metal roof installation?

Use self-drilling screws with gasketed washers sized to the panel and substrate, plus pancake screws for trim and closure strips at the eave and ridge. Underlayment is typically synthetic or felt over the deck, with ice and water shield at eaves, valleys and penetrations. The panel manufacturer's installation manual governs screw spacing and underlayment type, so follow that document and the local code edition.

How long does a metal roof installation take?

Duration is set by roof area in squares, panel length, trim and flashing count, deck repairs and weather, not by a standard schedule. Long panels that arrive pre-cut to the eave-to-ridge length go faster than field-cut sheets, and a tear-off adds a full day or more on many homes. We confirm the delivery date with the quote rather than promising one in advance.

How do you plan the panel layout before you learn how to install a metal roof?

Start with a measured takeoff: eave-to-ridge length in feet, total roof area in squares, panel width after overlap, and a count of ridge, eave, rake and valley trim in linear feet. Divide the eave width by the effective panel coverage to get the panel count, then add the manufacturer's waste allowance. That sheet is what you order from, and it is what keeps the installation sequence from stalling mid-roof.